PV351 NEW DRILL ASSEMBLING

Week 1 - Activities

  • Put the main frame on the supports
  • Positioning the components to be installed
    – Fuel Tanks
    – Water Tank
    – Pivot Shaft
    – Equalizer Bar
    – Front Jack Cylinder & Mast Support
    – Rear Jack Cylinders
  • Installed Front Jack Cylinders & Mast Support Assy
  • Installed Rear Jack Cylinders
  • Installed Fuel and Water Tanks
  • Installed Pivot Shaft and Equalizer Bar
  • Tightened and Torque all bolts
  • Connect all hose and lines
  • Installed A Frame
  • Installed RH and LH Track Frame
  • Connect all Hydraulic hose lines

Week 2 - Activities

  • Installed Rear Platform and Hand Rails
  • Installed Operator Cabin
  • Installed Mast Raise Cylinders
  • Installed all access ladders
  • Connect Electrical Systems
  • Connect Lighting Systems
  • Connect Emergency Shutdown Systems
  • Completed All Walkways and Hand Rails
  • Installed Engine muffler
  • Install Lighting System
  • Install and connect A/C System

Week 3 - Activities

  • Connect Cooling System hoses
  • Connect Engine Air Intake System
  • Completed Hydraulic System Lines
  • Connect all cables connections
  • Filled-up Hydraulic Oil
  • Filled-up Engine Fuel
  • Start the Engine
  • Check all leaks and verified machine condition
  • Load the machine to Lowbed
  • Transfer the machine for Mast Installation
  • Prepare The Mast for Installation

Week 4 - Activities

  • Mast Installation
  • Completed Mast Installation
  • Connect Front Balance Strut Bars
  • Connect Mast Raise Cylinder Pin
  • Final Checks and ready for Test and Commisioning